How to schedule your Christmas light install season

How to Schedule Your Christmas Light Install Season (Route Sheets, Crew Capacity, and Rain Days)

It is November 14th. Thirty-eight degrees, raining sideways, nine houses on today's board—three across town, two of them two-story, and one homeowner who has already called the office twice asking when you are coming. Your crew is in the truck with the heater running, waiting on you to decide something.

That morning is not a weather problem. It is a scheduling problem, and it was built back in August. I have been installing Christmas lights professionally since 2014 and I run a 43,000-member installer community, and the shops that finish December calm are almost never the fastest ones. They are the ones that built the calendar before they sold the first job.

Quick Answer: Build your Christmas light install schedule backward from December 5, not forward from October. Plan a two-person crew at 4 average homes per day, which gives roughly 160 house-slots across a 40-day install window, then book only 80% of that—about 128 houses—and hold the other 20% for weather, add-ons, and service calls. Group every day inside one subdivision or ZIP code, and hand each crew a printed route sheet with the tote number, footage, and gate code for every stop.

Why does the install schedule fall apart in November?

Three things break it, in the same order every year.

You booked to your best day, not your average day. A sharp two-person crew hits five or six homes on a dry 55-degree Tuesday. That becomes the planning number, the first cold snap arrives, and the whole board slides a week right.

You sold dates in the order the phone rang. A board that runs from one side of the county to the other burns 90 minutes in the truck—one entire house you did not install and did not get paid for.

You left no room for the season's real work. Add-ons, callbacks, and the customer who decides on December 1st that she wants the evergreens wrapped after all are not interruptions. They are a predictable percentage of every season, and a full calendar has nowhere to put them. Our guide to handling service calls and callbacks covers how to price and route that work.

How many Christmas light installs can one crew do in a day?

Use these as planning numbers, not personal records. They assume strands are already pre-bulbed and pre-clipped at the shop, which is the single biggest lever on your daily house count.

Job type Two-person crew time Realistic per day
Single-story ranch, roofline only (100–140 ft) 60–75 min 6–7
Two-story roofline plus peaks (180–220 ft) 90–120 min 4–5
Full package: roofline, 2 wrapped trees, 6 bushes, wreath 2.5–3.5 hrs 2–3
Large estate or heavy custom design 4–6 hrs 1
Commercial property Half day to full day 1
Takedown of your own install 20–35 min 10–20

Plan the season at 4 homes per crew per day. Not 6. When the crew beats the board you get a free hour for a callback or tomorrow's first house. When you plan at 6 and get 4, you are calling customers to move their date, and that is the call that costs you the renewal. For where the minutes actually go, read how long a Christmas light install really takes.

The fastest way to raise that daily number is not hustle. It is method—bulb and clip as one motion instead of two:

How do you build the season calendar?

Build it backward. Every home you install must be lit before the homeowner's own Christmas starts, and for most families that is the first or second weekend of December, not the 24th.

  1. Set the hard finish date at December 5. Everything after it is overflow, not plan. Your season calendar for selling, installing, and taking down should already have this date circled.
  2. Set the start date at October 20. Some markets start the first week of October. Earlier than that and you are fighting warm weather and homeowners who are not thinking about Christmas yet.
  3. Count your real install days. October 20 to December 5, six days a week, is roughly 40 install days per crew.
  4. Multiply by 4. One crew equals about 160 house-slots. Two crews equal 320.
  5. Book to 80%. One crew sells 128 houses, not 160. The 32 open slots are your weather insurance, your add-on capacity, and your service window.
  6. Assign every sold job to a date the day the deposit lands. A job without a date on the board is not scheduled, it is remembered—and remembered jobs are the ones that get called on December 3rd.
  7. Lock supply and staffing against that number. 128 houses at an average 190 linear feet is about 24,000 feet of C9 stringer. Order against the calendar, not last year's feeling. Our supply ordering and inventory planning guide walks the lead times, and hiring and training your crews should be finished before the first install day, not during it.

What that looks like in dollars. One two-person crew, 128 booked houses, an average ticket of $1,747, is $223,616 for the season. Push the same crew to a 160-house board and you do not earn 25% more—you earn overtime, callbacks, and a stack of moved dates. What you keep out of that revenue is a separate conversation; see real Christmas light business profit margins.

The daily route sheet for a Christmas light install crew

What goes on a daily route sheet?

Every crew gets a printed sheet before they leave the shop—printed, because phones die on a truck in December and a sheet on the dash gets checked. It turns a list of addresses into a day that runs itself.

Field on the sheet Why it is there
Stop order, 1 through 5 Removes the daily argument about which house is next
Tote number One labeled tote per house, staged the night before
Linear feet, peak count, tree and bush count The crew knows the scope before the ladder comes off the rack
Bulb color and spacing (12″ or 15″) Prevents the wrong strand going up on the wrong roof
Outlet location and cord run notes Power is the #1 hidden time sink on an unfamiliar house
Gate code, dog, alarm, parking note Kills the 15-minute wait for a callback from the office
Homeowner name and cell The crew texts an ETA from the previous driveway
Photo checkbox No stop closes without a lit photo for the file and the renewal

Stage the totes the night before, one per house, labeled with the number on the route sheet. Zip-tie labels inside each tote do the rest: red for the right side of the house, a second color for peaks, and a count marking the floor. Those labels are what make takedown fast in January, and they are why storing lights properly between seasons pays you back a year later. Load the truck against the sheet too—our truck and trailer setup guide covers what lives on the rack permanently versus what changes daily.

How do you group jobs so your crews stop driving?

Drive time is the most expensive thing on your P&L that nobody puts on an invoice. The rule is simple: no crew leaves a subdivision until every job in that subdivision is done.

Sort the booked list by ZIP, then by street, then build days out of those clusters. If a day has one orphan house 22 minutes away, it moves to the day you already have three jobs near it. A tight day of five houses inside one neighborhood beats a scattered day of five houses across the county by close to an hour of paid labor—and the neighbors watch your crew work the same street two days running. That is free marketing, and it compounds: our guide to building route density shows how to deliberately sell the houses next door to the ones you already have.

Sales speed feeds the same machine. A quote that goes out in 5 to 20 minutes, while the homeowner is still on your website, lets you drop that job onto the exact day that fills a hole in an existing cluster—see how to quote a house in under 20 minutes.

What do you do on a rain day or a wind day?

You are going to lose days. Plan five of them per season and you will be close. What separates a lost day from a lost week is having the call already made before the crew asks.

Condition Roof and ladder work What the crew does instead
Light rain, above 40°F Crew's call; standoff mandatory Run the day, lead with ground work
Steady rain Stop Bushes, wrapped trees, stake lighting, cord runs
Frost or ice on the roof Stop, no exceptions Ground work only, or go back to the shop
Wind above 20–25 mph Stop, no exceptions Shop day: pre-bulb, pre-clip, bench-test
Below 20°F Shorten the day Wire stiffens; warm strands in the truck cab

A shop day is not a wasted day. Two people pre-bulbing and pre-clipping for six hours build most of a week's strands, which buys back time on every install day after it. Aluminum ladders are fine in the cold and always have been—the fiberglass rule is a myth—but a standoff is not optional on any roof, wet or dry. For the rest of the weather playbook, read installing in cold weather and snow and the complete installation safety guide.

Two rules for the makeup: hold every Friday in November open until Thursday night, and never move a customer twice. The second move is when they stop believing the date.

One thing is never on a rain-day list: touching a homeowner's GFCI. If an outlet is dead or tripping, you find the water—elevated connections, sockets turned down, drip loops in every cord—and you never tape or seal a connection, because tape traps water and creates the exact trip you are chasing. Testing or replacing a homeowner's GFCI is a licensed electrician's job, not yours.

How do you schedule takedown in January?

Takedown is included in your $8 to $12 per linear foot. It is the red carpet part of the service, and it is the part most shops fail to schedule until the phone starts ringing on December 27th.

Build the takedown board in December while every install is still fresh, sorted the same way: ZIP, then street. The crew that installed the house pulls it in 20 to 35 minutes, which is 10 to 20 houses a day. Bulbs and clips stay on the strands. Circle wrap each run, drop it in the tote it came out of, and let the county number on the tote tell you where it goes on the shelf. Standalone takedowns—houses somebody else installed—are $75 to $200 and get their own days, because you do not know what is up there or how it is fastened. The full breakdown lives in our takedown pricing, process, and profit guide.

Schedule the money too. January and February are the cash gap in this business. The takedown board is also your renewal list—every tote you pull in January is a customer to call in August, which is how customer renewals get to 80%.

A home lit in red and warm white on Christmas Eve

Sell the date, not the calendar

The date is the product. Not the lights. Nobody has ever pulled into the driveway on Christmas Eve with the grandkids in the back seat and felt something because of linear footage. They feel it because the house is glowing and the kids go quiet for a second. That magical moment is what you sell, and the install date is the only thing standing between the homeowner and it.

So put the date at the center of every conversation, starting on the phone:

"Hi, I'm Jason with [Your Company]. How can we help you with this amazing, magical Christmas season? We want to make this magical." Then: "What are you looking for?" Then: "Have you ever had Christmas lights professionally installed?" If they have, ask what they liked about the last company and what they did not. If they have not, explain what separates you—starting with the fact that you commit to a date and keep it.

Most homeowners want a quote online, so send one the same day, inside 5 to 20 minutes if you can, with a payment link and an AI mock-up of their own house lit up. If they want you out there, offer two specific times—"Tuesday at 3 or Thursday at 5"—and text a confirmation with your name, your photo, and an ETA. On the walkthrough, walk beside them, talk about who is coming for the holidays, and say the visuals out loud: "we would wrap those two evergreens, and a big 60-inch wreath on that gable would be incredible." Then step out to the truck, build the quote, and come back in: "I'd love to come back inside and go over it at the kitchen table with you." Never in the driveway. Never emailed ahead of the close.

Our packages start at $1,200, most homes land between $1,500 and $2,000, and the quote ends in seven—$1,247, $1,747, $2,147. Then the close that protects your calendar: a 30% to 50% deposit, with options. The deposit secures their date. It is never "to buy materials." Materials are your problem. The date is theirs, and the moment it is paid for it goes on the board with a tote number waiting for it.

Next step: a schedule is only as good as what fills it, and the cheapest houses to install are the ones next door to houses you already have. Read how to build route density and start selling your booked streets before October.

Stock the gear that makes a tight schedule possible: C9 LED stringers and bulbs, complete pro light kits, and enclosed Christmas light clips. Size a job before you schedule it with the free Christmas light calculator, and if you want the whole operating system instead of one piece of it, that is what our installer training is built for.

Related Guides

Frequently Asked Questions

How many Christmas light installs can a two-person crew do in a day?

Four average homes is the number to plan on. A strong crew with pre-bulbed, pre-clipped strands and a tight route can hit five or six single-story rooflines on a good day, but scheduling at your best day is what causes moved dates in November. Plan at 4, celebrate 6.

When should I start scheduling my Christmas light installs?

Build the calendar in August and assign dates from the day the first deposit lands. Installs start around October 20 in most markets, but the board that carries you through December has to exist before you sell into it, or you will sell more days than you own.

What should I do when it rains on an install day?

Move roof and ladder work off the day and run ground work instead—bushes, wrapped trees, stake lighting, and cord runs. Stop all roof work entirely for frost, ice, or wind above 20 to 25 mph, and turn that day into a shop day of pre-bulbing and bench-testing. Hold Fridays in November open as makeup days.

Should I let customers pick their own install date?

Offer a window, not a date, until the deposit is paid. Once 30% to 50% is down, assign a specific day inside the cluster their street belongs to and confirm it in writing. The deposit secures the date, which is exactly why customers respect it.

How far in advance should I schedule takedowns?

Build the takedown board in December, before the season ends. Sort it by ZIP and street the same way you sorted installs, plan 10 to 20 houses per crew per day, and start the first week of January. Takedown is included in your $8 to $12 per linear foot for your own installs; standalone takedowns of somebody else's work run $75 to $200 and get their own days.


About the author: Jason Geiman has been installing Christmas lights professionally since 2014. He is the founder of ChristmasLightsHQ, the supply and training resource built for professional installers, and he runs a 43,000+ member installer community where contractors share real numbers from real seasons.